Provision To Supply Manpower Tool & Equipment For Pipeline Inspection Using Calliper/Geometry & Magnetic Flux Leakage (MFL) Tool Turboducto Nico Lopez Pipeline
The execution of the interior inspection services with the use of the GEO and MFL (Magnetic Flux Leakage) tool. For the detection of all types of anomalies in the Varadero – Matanzas Pipeline, 72.9 km long and 20 in diameter, and the Turbo Pipeline from the Ñico López refinery to the ECASA Fuel Base, with a length of 38 km and a diameter of 10.
- Pipeline 1: 10-Inch x 38 km Turboducto Ñico López
- Pipeline 2: 20-Inch x 72.8 km Crude Pipeline from Varadero – Matanzas (LMO)
- Pipeline 3: 16-Inch x 32 km Gasoducto Energas – Punto Cero
Total manhour for this project is 28,512.
SCOPE OF WORK
- Provision to Supply Manpower Tool And Equipment For Pipeline Inspection Using Caliper/Geometry & Magnetic Flux Leakgae (MFL) Tool For Turboducto Nico Lopez Pipeline 1×10”X 38km
- To prepare in line inspection tools for the specific requirements of the project.
- To conduct testing of tools using mock operation.
- To mobilization and demobilization of personnel and equipment to the client specified mobilization point.
- To inspection data analysis to agreed standards and specifications
- To provide immediate on-site field report.
- To complete a final inspection report within 60 days of project completion.